Hurricane Milton damaged all 27 facets of this 69-square St. Petersburg clay tile roof. After a core test ruled out a code-compliant spot repair, the roof was rebuilt tile off, tile on as a Verea Clay S Barrel system in the Fume mix over 2-ply Polyglass underlayment, with color-matched mortar and full property protection. Told from the project record, with the client's details redacted.

At a glance

The shape of this job

The short version, before the narrative: what was installed, what the roof was, and how the decision was settled.

System installed
Verea Clay S Barrel, Fume mix, over 2-ply self-adhered modified bitumen
Roof type
Clay tile, Spanish S profile
Service line
Roof replacement, tile off and tile on
Market
St. Petersburg, FL
Scale
69 squares across 27 facets

Problem

Hurricane Milton damaged all 27 facets of this clay tile roof on October 9, 2024. The aerial measurement recorded 69 squares of tile, 407 feet of hips, and 161 feet of valleys.

Decision

The January 17, 2025 core test cut, exposed, and measured the existing self-adhered cap sheet. At more than 90 mils, the bonded membrane tore instead of peeling, so a clean, code-compliant partial repair was not possible and the roof was rebuilt tile off, tile on.

Result

A Verea Clay S Barrel roof in the Fume mix over Polyglass MTS Plus and TU Plus, with 477 linear feet of mortar-bedded hips and ridges and 515 feet of clay bird stops. The Certificate of Completion was signed April 3, 2026.

St. Petersburg, FL · From the file

The job on record

Each fact below comes from the underlying project record: measurement reports, material orders, written scopes, dated photographs, completion paperwork, or an owner-attested narrative.

Roof
69 squares, 27 facets
Roof covering
Verea Clay S Barrel, Fume mix
Underlayment
2-ply self-adhered modified bitumen
Tile attachment
Stainless screws + tile foam adhesive
Hip and ridge
477 linear ft, mortar-bedded
Eave closures
515 linear ft of clay bird stops
Driveway protection
1/2-in plywood + composite Duradeck
Roof process
Under 8 days, City inspections included
Completion certificate
Apr 3, 2026
Owner storyboard
20 published project photographs
Job file
103 documents, 618 pages

Document the Milton damage

Hurricane Milton damaged every facet of this two-story waterfront St. Petersburg roof on October 9, 2024. The aerial measurement records 69 squares of clay tile across 27 facets, with 407 feet of hips and 161 feet of valleys.

A 71-photo drone survey on November 23 documented the damage from the air and at close range. The November 27 measurement report fixed the overall roof dimensions before repair-versus-replacement work began.

Use the core test to settle repair versus replacement

The January 17, 2025 core test cut, exposed, and measured the existing self-adhered cap sheet. At more than 90 mils thick, the bonded membrane tore instead of peeling, so a clean, code-compliant partial repair was not possible and the roof had to be rebuilt tile off, tile on.

The January 22 carrier-ready documentation package brought together the scope, aerial measurements, core-test findings, Florida Building Code citations, FRSA-TRI tile standards, and product approvals.

Carry the documented scope through approval

Seventeen months of documentation and scope discipline separate the storm from the first day of tear-off. The City of St. Petersburg issued the re-roof permit on March 6, 2026, for a tile-off, tile-on replacement.

The same job file documents interior storm damage, including laser-level photographs of buckled second-floor flooring. That restoration proceeded through vetted specialty subcontractors while the roof record stayed focused on the permitted re-roof.

Protect the property before the roof

The clay brick driveway received a staggered layer of 1/2-inch plywood, then composite Duradeck as a second layer. Together, those layers spread the loads from heavy machinery, heavy dump trailers, and vehicle traffic to prevent cracking, chipping, or pitting.

The entire perimeter was protected, openings were boarded, the pool cage was tarped, and plywood boxes covered exposed air handlers and pool equipment. The pool had to be re-tarped several times during the build, then received a full deep clean after the roof was complete.

OSHA-compliant tear-off to the deck

With the protection in place, the roof was removed under an OSHA-compliant tear-off process that continued to the deck. Tear-off began March 10, and the deck was covered with the new base sheet by March 11. The photographic sequence records tile removal, debris staging, heavy-equipment transfer, and dump-trailer loading.

Perimeter tarps, boarded openings, equipment boxes, driveway protection, and the pool cover remained part of the working setup through the tear-off.

Build the two-ply tile system

The dry-in was a 2-ply self-adhered modified-bitumen underlayment system: Polyglass MTS Plus as the base layer and TU Plus as the top layer.

The roof covering was Verea Clay S Barrel, the Spanish S profile, in the Fume mix. Every field tile was mechanically attached with a stainless steel screw plus tile spray foam adhesive, and the ridges were attached the same way.

Clay bird stops closed 515 feet of eaves, and new Galvalume W-profile metal ran every valley. The 477 linear feet of hips and ridges were set on channel-metal nailers in a full mortar bed.

Mix and seal the mortar

The mortar was custom-blended batch by batch with charcoal and brown oxide dye to match the Fume tile blend, then mixed with Sikalatex additive to fortify the blend and lengthen the dye's lifespan.

Every mortar joint was then sealed with a penetrating siloxane matte sealant to further waterproof the joints and prevent algae growth.

Close out the documented roof

The owner-attested record counts the active roof process at under eight days, including the required City of St. Petersburg mid-roof inspections. The job file separately preserves the dated milestones across staging, inspections, tile installation, and closeout.

The finished roof was documented from above on April 2, closing the sequence that began with the Milton damage survey and core test. The Certificate of Completion was signed April 3, 2026.

Sequence on record

How the work ran

Each milestone below comes from a document, dated photograph, or owner-attested project record.

  1. Oct 9, 2024

    Hurricane Milton damages all 27 facets of the clay tile roof.

  2. Nov 23, 2024

    Drone damage survey completed with 71 aerial photographs.

  3. Nov 27, 2024

    Aerial measurement report records 69 squares across 27 facets.

  4. Jan 17, 2025

    Core test finds that the old self-adhered cap sheet tears instead of peeling, ruling out a code-compliant spot repair.

  5. Jan 22, 2025

    Full documentation package delivered with scope, measurements, core test, code citations, tile standards, and product approvals.

  6. Mar 6, 2026

    City of St. Petersburg permit issued for "Re-roof. Tile off, tile on."

  7. Mar 10 to 11, 2026

    Property protection is installed, OSHA-compliant tear-off reaches the deck, and the MTS Plus base-sheet dry-in is completed.

  8. Mar 17 to 18, 2026

    TU Plus top sheet completed and new Verea clay tile loaded on the roof.

  9. Mar 21 to 27, 2026

    Field tile installed; hips and ridges set in custom color-matched mortar.

  10. Apr 2, 2026

    Completion photographs flown.

  11. Apr 3, 2026

    Certificate of Completion signed.

  12. Owner-attested duration

    The active roof process totals under eight days, including required City mid-roof inspections.

From the job

The job in photographs

Photographs from the job's own documentation, in work order. Details that could identify the client or the property are cropped or blurred.

Before

Straight-down aerial view of the existing brown barrel tile roof before replacement
The existing clay tile roof, documented from above before replacement.
Close-up of broken brown barrel tiles with a hole exposing gray roof material below
Broken tile and exposed roof layers, documented at close range.
Close aerial view of broken and displaced barrel tiles beside an open metal valley
Damage documented around a metal valley and the adjoining tile field.
Roof hip with cap tiles missing, exposing the metal channel nailer that anchored them.
The job-file survey records missing hip caps and the exposed channel-metal nailer.
Close-up of a square core-test cut in gray granulated underlayment surrounded by removed clay tile pieces
A core-test cut through the existing granulated underlayment.
Thickness gauge held against the cut edge of gray granulated roof underlayment
A thickness gauge records the cut membrane edge.
Thickness gauge placed against the black underside of a cut roof membrane sample on gray granulated underlayment
The core-test sample exposes the membrane layers for measurement.
Old modified bitumen membrane torn during peel-back, exposing the wood deck beneath.
The job-file core test shows the bonded membrane tearing instead of peeling cleanly.

During the work

Two-story home with plywood and composite mats covering the clay brick driveway and a telehandler beside the curb
Staggered 1/2-inch plywood under composite Duradeck spread machinery, trailer, and vehicle loads across the clay brick driveway.
Plywood box built over two outdoor air-conditioning units with blue tarps covering the ground around the house
A plywood box protects exposed equipment while perimeter tarps catch tear-off debris.
Roofing crew removing tile above boarded windows while a telehandler stands on the protected driveway
OSHA-compliant tear-off underway with openings boarded and machinery on the protected driveway.
Roof-level view of a debris bin filled with removed clay tile beside the remaining tile field
Removed clay tile collected in the debris bin during tear-off.
Telehandler tipping removed clay tile into a dump trailer while roofers continue tear-off on the house
Removed tile transferred into a heavy dump trailer while tear-off continues.
Aerial view of crews working across roof slopes stripped of tile with blue tarps covering the pool and patio below
Tile removed across the main slopes as the crew works to the deck; the pool and patio remain tarped.
Wrapped pallets of underlayment staged on plywood covering the clay brick driveway
Underlayment pallets staged on the driveway protection before dry-in.
Front aerial view of crews installing teal underlayment across the main roof while tear-off continues on a lower section
MTS Plus base sheet advances across the main roof while tear-off continues on a lower section.
High aerial view of teal base sheet and gray cap sheet advancing across multiple roof slopes
The 2-ply system going down: Polyglass MTS Plus base, TU Plus top layer.
Aerial view of the roof fully covered in gray printed underlayment with seams and penetrations sealed
Dry-in complete with the TU Plus top layer sealed around transitions and penetrations.
Straight-down aerial view of new clay tiles distributed in rows across the dried-in roof
Verea Clay S Barrel tiles distributed in rows across the dried-in roof before installation.
Close view of newly installed barrel tile with ridge caps running along intersecting roof lines
Ridge tiles use the same stainless-screw and tile-foam attachment as the field tile.

Finished

Close view across the finished Fume-blend clay tile field and mortared hip and ridge lines
Completed Fume mix and mortar joints, sealed with a penetrating matte siloxane.
Straight-down drone view of the finished light brown barrel tile roof with a swimming pool beside the house
Finished Verea Clay S Barrel roof in Fume, documented from directly above.

The paperwork

Documents from the file

Shown as delivered, with the client's details blacked out. Black bars are the redactions; everything else is untouched.

Re-roof permit summary
City of St. Petersburg permit summary for a residential roof replacement over 40 squares, tile roof, 6/12 pitch, with identifying details blacked out.

Owner name and mailing line, street address, parcel ID, application and pin numbers, access code, valuation, and fees are blacked out.

Certificate of Completion
Certificate of Completion for the re-roof dated April 3, 2026, with customer details and the signature block blacked out.

Customer name, job address, and the signature block name and signature are blacked out.

Where this comes from

One job, one file

Built from the owner-supplied job file evidence record prepared July 14, 2026, containing 103 documents and 618 pages, plus the owner's attested Verea Clay S Barrel narrative and 20-photo storyboard dated July 16, 2026. Every fact on this page traces to one or both records; the complementary job-file photographs and closeout artifacts shown here were redaction-cleared before publication.

What you will not find here: the client's name or address, claim or policy numbers, the insurance company, dollar amounts, or how anything went with insurance. That stays the client's business.

See the other case studies

What this job answers

The questions a job like this settles

Every answer below is drawn from the record on this page. Nothing here predicts what your roof will need; it shows how these questions were settled on one documented job.

Can't the broken tiles just be replaced?
On this roof, no, and the record shows why rather than asserting it. The core test cut, exposed, and measured the existing self-adhered cap sheet: at more than 90 mils thick, the bonded membrane tore instead of peeling, which rules out a clean, code-compliant partial repair.
What happens to the driveway and pool while machinery is here?
The clay brick driveway took a staggered layer of 1/2-inch plywood under composite Duradeck, spreading the loads from heavy machinery, dump trailers, and vehicle traffic. The perimeter was protected, openings were boarded, the pool cage was tarped, and plywood boxes covered exposed air handlers and pool equipment. The pool was re-tarped several times during the build, then deep cleaned once the roof was complete.
How long is the roof open?
The owner-attested record counts the active roof process at under eight days, including the required City of St. Petersburg mid-roof inspections. The documentation and approval work ahead of it took far longer: seventeen months separate the storm from the first day of tear-off.
Will new mortar match the tile?
The mortar was custom-blended batch by batch with charcoal and brown oxide dye to match the Fume tile blend, then mixed with Sikalatex additive to fortify the blend and lengthen the dye's lifespan. Every joint was sealed afterward with a penetrating siloxane matte sealant.